How To Read This Page
Wheeler - Understanding Variation defines the handful of numbers we watch on Claude’s runs. This page is the evidence behind them. Each section below is one of those variables, and under it are the runs — in the order they happened — that taught us what the variable means. Read a section top to bottom and you see how our understanding of that one number grew.
The premise throughout (from Goldratt - Diminishing A Limitation and Wheeler): when two runs of the same test diverge, the cause is in what they share — the test, the spec, the harness — not in the model having a bad night.
One thing the runs changed our minds about: we started out believing every wide gap was a defect to hunt down and fix. It wasn’t. Many are ordinary noise, and the real fixable signal is almost always the input — a test that is too big, too vague, or given out of order. That shift is what the timelines below show.
The raw numbers live in three metrics sheets, one per model/era: opus (run 65 onward), sonnet pairs, and older sonnet triples. The charts in the per-run reports cover the opus era — run 65 onward; the earlier sonnet runs aren’t charted here, but their data is in the sheets if you want to look.
green time pair range
The gap between the two runs of the same test (|green a − green b|). Two runs of a clear, well-specified test land close together; a wide gap means something made them diverge.
- Rebuild 44/45 — the first wide pairs, both traced to an under-specified prompt step, not the worker — and the early lesson that “which file got patched” tells you about the spec, not the prompt.
- Rebuild 48/49, 50/51, 56/58 — each wide pair was a prompt/spec gap (an annotation the report never produces; a prompt pointing at a file that doesn’t exist; a silent prompt branch). The output was near-identical; the variance was all in the path the worker took.
- Rebuild 52/53 — the first pair to break the upper limit: a point outside the limit is a cleaner, stronger signal than a merely wide one.
- Rebuild 54/55 — a wide pair with byte-identical output exposed a harness bug (a coverage shortlist that never wrote a single byte). The signal catches broken infrastructure, not just the model — and CI never noticed because both runs passed.
- Rebuild 65/66 — a wide pair meant architecturally different code, a fork seeded by the very first scenario.
- Rebuild 67/68 — the turning point: a wide pair with identical code and no findable cause. A wide range is a signal to investigate, not proof of a defect — the verdict was “common cause, no action.”
- Rebuild 69/70 — same final code, one expensive tool choice (a subagent vs an inline search): same outcome, different path.
- Rebuild 73/74, 79/80 — the wide pair was the clock, not the test: the two runs ran hours apart and the gap was server speed (in 79/80 the faster run even produced more work). This is what forced us to control the timing.
- Rebuild 75/76, 77/78 — common-cause wide pairs; 77/78’s width was simply that the test is big, not defective.
- Rebuild 83, 84, 85, 86 — once the two runs go concurrently from the same commit, the timing confound is gone; a wide range now points at how much each half explored, and these batches stay in control.
green time pair range moving range
How much the pair range jumps from one test to the next. Because tests are ordered shortest-to-longest, the pair range is expected to widen gradually; a sudden jump — not the gradual rise — is the signal.
- No run has produced a finding here yet. This is a gap we’ll fill as more batches come in — left visible on purpose.
green time
The green-phase time of a single run (we keep the shorter of the pair). Over the limit but under the timeout = a test too big or under-specified, so Claude has to guess. At the timeout = a contradiction, or Claude trying to build a dependency it isn’t allowed to add.
- Rebuild 47 — green-phase scope creep: a run did far more editing than its failing test required (a validator run inside the fix step, then chasing every finding).
- Rebuild 50/51, 52/53, 54/55, 56/58, 65/66 — long green times from build-retries, exploration overhead, and improvised checks. No contradictions — just extra work before the same edit.
- Rebuild 67/68 — the long run wrote the same code; the length was deliberation (re-proving a fact the test had already pinned), not a harder scenario.
- Rebuild 75/76 — the first scenario is intrinsically the longest (it creates ~10 files), giving any divergence more room to open up.
- Rebuild 77 — the green-time control chart itself: six runs all in control; the compile sub-phase is stable, the verify sub-phase carries the variance.
- Rebuild 77/78 — the clearest “too big” case: the widest relative range belongs to the tests that create brand-new logic. The fix is an input fix — split them smaller.
- Rebuild 84, 86 — the longest scenario is the framework-founding first one; no timeouts, so no contradictions in this era.
green time moving range
How much the green time jumps between consecutive tests. Ordered shortest-to-longest, it should rise gradually; a leap flags a test that demanded too big a jump in understanding.
- Rebuild 77 — the only run to chart it so far: the green-time series was stable, the largest leap well under its limit, so the process is not drifting. More data is needed before this thread says much.
scale & green tokens
Output tokens measure how much work a run did, independent of how fast the server ran that day. They feed the scale that normalizes for server speed — and they tell a real work difference apart from a slow-server day.
- Rebuild 44/45 → 77/78 — every early study compared two runs taken hours or days apart, so server/time-of-day decode speed was baked into the pair range and couldn’t be separated out. Tokens were usually comparable, so the variance was tool-call count, not text volume.
- Rebuild 67/68 — one run produced far more tokens for the same commit: green cost is about how much the worker thinks before writing, not how much it writes.
- Rebuild 73/74, 79/80 — the canonical server-noise cases: the wide pair was almost entirely server decode rate (79/80’s faster run even emitted more tokens). This motivated normalizing per-token rate and running pairs at the same time.
- Rebuild 83 — derived the token-scaled pair-range: a similarity threshold decides whether the two halves did equivalent work, and the slower half is scaled to the faster’s rate to isolate real work from rate overhead.
- Rebuild 84 — tokens are a second, orthogonal axis: ranking by token divergence surfaced pairs the wall-clock range missed (a fast-decode day hid the extra work). Screen on both.
- Rebuild 85 — but a green token is ~70–84% tool-orchestration churn, not thinking or output: the widest token-gap pair produced byte-identical code. So tokens measure exploration depth, not divergent output — the wall-clock range stays the primary signal.
- Rebuild 86 — token-scaling can over-promote a tiny range; cross-check against the raw range so noise doesn’t get surfaced as a top pair.
warm-up position
The first test in a run is special: it builds the test-automation scaffolding every later test reuses, so it is the longest and most variable. It’s a different process and should be set apart from the rest.
- Rebuild 65/66 — the first scenario forks (invent-and-delegate vs inline), and every later scenario copies it: a wide range three tests later was really decided at test one.
- Rebuild 75/76 — the first scenario ran “cold” and went hunting for dependencies it should have just created; fixed by having it read the specs first.
- Rebuild 77 — the framework-founding first scenario has the longest green and should carry its own baseline, not be pooled with the rest.
- Rebuild 86 — the lone over-limit point was the first scenario; its width is one-time framework cost, not a defect — stratify it out.
Where This Leaves Us
Read together, the timelines say the harness is in statistical control: most wide pairs now resolve to ordinary noise or to the test simply being big, and the recurring near-special-cause is the warm-up scenario — a known, structural thing, not a defect. So the work has moved off the harness and onto the inputs: the size, ordering, and spec-detail of the test cases (see Deming - Building Quality In for who owns that, and Wheeler - Understanding Variation for the charts).
Two threads above — the two moving ranges — are still nearly blank. They’re newer than most of these runs, so the history hasn’t been written yet. As more batches come in, that’s where the next understanding gets recorded.